Plant Machinery Analysis

Capacity of each machine in a finishing plant: speed, set-up time, efficiency, double passes and the share of fabric that visits it.
CapacitySet-up & efficiencyBottleneck

Capacity is speed × time × efficiency — and efficiency hides the set-ups

For a continuous machine the run of 10,000 m at 50 m/min takes 200 min, but each run also needs cleaning (30 min) and preparation and matching (60 min). The calculated efficiency is run time ÷ (run + set-up); subtract another 10% for miscellaneous losses. A machine that passes the fabric twice (double thermosol, dye + wash) has its capacity halved for that fabric. The plant’s overall capacity is the bottleneck.

Thermosol dyeing range — capacity for a 10,000 m run
AB
1Proposed run size (m)
2Speed (m/min)
3Production time for one run (min)200.0
4Average cleaning (min)
5Average preparation and matching (min)
6Set-up time per run90
7Calculated efficiency69.0%
8Miscellaneous efficiency losses
9Net efficiency59.0%
10Machines
11Capacity of machine (m/day)42,455
12Share of fabric needing a double pass
13Capacity adjusted for double pass (m/day)33,964
blue = input (edit me)grey = formula (click to see it)

The whole plant

MachineSpeed m/minEfficiencyCapacity m/dayNotes
Singeing, desizing, scouring & bleaching12080%138,240one machine or split in two; long bleaching runs
Mercerizing5080%57,600 (155,520 overall)only 50/135 of the fabric is mercerized
Thermosol dyeing5059%42,455 → 34,0003,000 yd minimum run; double passes
Pad steam (dyeing + washing)7057%57,571 → 46,000set-up 70 min
Stenter for dyeing5059%42,455 → 34,000
Stenters for setting & finishing (2)9080%207,360 ÷ 2.25 = 92,160double pass for all non-stenter-dyed fabric, sometimes after mercerizing
Printing5067%48,185set-up 60 min; less for colour change, more for design change
Calendering7080%80,640 (201,600 overall)40% of fabric
Sanforizing7080%80,640 (161,280 overall)50% of fabric

Overall: dyeing and printing capacity = continuous 34,000 + batch 10,000 + stenter-dyed 34,000 + printing 48,185 ≈ 126,000 m/day; finishing = 34,000 + 92,160 ≈ 126,000 m/day. The plant is balanced at about 126,000 m a day; the thermosol and stenter-dyeing ranges, at 34,000 each, are the lines to watch.