Textile Costing · Lecture 19

Review of Weaving Calculations II

Loom production per day, B-grade adjustment, sizing and packing cost — the variable production cost of one metre of grey fabric.
Loom productionB-gradeSizing costVariable cost per metre

Production of a loom

An air-jet loom at 800 rpm inserting 60 picks per inch at 90% efficiency makes 12 inches a minute: 800 × 0.9 ÷ 60. Per day that is 480 yd; 1% of it is B-grade, so 475 yd of A-grade — 435 m. Sizing is paid per kg of sized warp; packing per metre; B-grade fetches a lower price that comes back as a small credit.

Loom production and variable cost per metre
ABC
1RPM
2Efficiency
3Picks per inch
4Production per minute (in)12.00in
5Production per day (yd)480.0yd
6B-grade
7A-grade production per day (yd)475.2yd
8A-grade production per day (m)434.5m
9Variable production cost per metre
10Yarn cost per metre (from Lecture 18)
11Warp weight per yard before wastage (lb)
12Warp contraction
13Sized warp per metre (kg) — all wastage assumed in warping0.124kg
14Sizing cost per kg
15Sizing cost per metre1.24
16Packing cost per metre
17B-grade price per metre
18B-grade proceeds per metre (credit)(0.21)
19Total variable production cost per metre29.32
blue = input (edit me)grey = formula (click to see it)