Budgets & Variances

The budgeting cycle, static and flexible budgets, and Level 0 to Level 2 variance analysis for Webb Company.
Master budgetStatic vs flexibleLevel 2 analysis

Why budget

Budgets are among the most widely used tools for planning and controlling organisations. A budget is a quantitative expression, for a set time period, of a proposed future plan of action. It turns managers’ perspectives forward — to exploit opportunities and to anticipate problems. The budgeting cycle: (1) plan the performance of the organisation and its sub-units; (2) provide a frame of reference against which actual results are compared; (3) investigate variations from plan and take corrective action; (4) plan again with the feedback. The master budget coordinates all the individual budgets — operating decisions on acquiring and using resources, financing decisions on how to pay for them.

A variance is the difference between an actual result and a budgeted amount. A standard is a carefully predetermined amount, usually per unit. A static budget is based on one level of output and is not altered afterwards; a flexible budget is adjusted to the actual output, which lets managers compute a richer set of variances. A variance is favourable (F) if it increases operating income relative to budget and unfavourable (U) if it decreases it.

Webb Company — April 2007

Webb makes a jacket sold to clothing stores. Budgeted selling price 180; budgeted variable cost 99 per jacket (materials 60, direct manufacturing labour 16, variable manufacturing overhead 12, direct marketing labour 6, variable marketing overhead 5); budgeted fixed costs 710,000 (276,000 manufacturing, 434,000 marketing). The static budget assumed 12,000 jackets; 10,000 were actually made and sold.

Level 0, 1 and 2 variance analysis
ABCDEF
1Actual resultsFlexible-budget varianceFlexible budgetSales-volume varianceStatic budget
2Units sold010,000(2,000)
3Budgeted price / unit variable cost / fixed cost
4Revenues50,0001,800,000(360,000)2,160,000
5Variable costs130,000990,000(198,000)1,188,000
6Contribution margin730,000(80,000)810,000(162,000)972,000
7Fixed costs(5,000)710,0000710,000
8Operating income25,000(75,000)100,000(162,000)262,000
9Static-budget variance (Level 0)(237,000)
blue = input (edit me)grey = formula (click to see it)

Reading the sheet: the static-budget variance of operating income is 237,000 U (Level 0). Level 1 splits it line by line against the static budget. Level 2 inserts the flexible budget at 10,000 units: the sales-volume variance (162,000 U) comes purely from selling 2,000 fewer jackets, while the flexible-budget variance (75,000 U) is what the operating managers can really be held to — revenue 50,000 F (price higher than budget), variable cost 130,000 U, fixed cost 5,000 F.

The five steps of a flexible budget

  1. Determine the budgeted selling price, unit variable cost and fixed costs.
  2. Determine the actual quantity of the revenue driver (10,000 jackets sold).
  3. Flexible-budget revenue = budgeted price × actual quantity = 180 × 10,000 = 1,800,000.
  4. Determine the actual quantity of the cost drivers (units produced and sold).
  5. Flexible-budget costs = budgeted unit variable cost × actual quantity + budgeted fixed cost = 990,000 + 710,000.